Scheduling a Job

This document covers the following topics:


Defining Scheduling Parameters for a Job

This feature allows you to define a schedule for a job master or an active job. You can define the time frame for the schedule, insert a message, assign account information and edit the schedule dependency information.

Start of instruction setTo define scheduling parameters for a job

  1. In the object workspace, open a Job Master instance.

  2. In the Maintenance Job Master or Maintenance Job Active window, open the tabbed page Scheduling Parameters.

    For a job master, the page looks similar to the following example:

    graphics/jobmaster_schedulingparameters.png

    For an active job, the corresponding page looks similar to the following example:

    graphics/jobmaster_active_schedulingparameters.png

  3. Make your definitions. The fields contained in the window are explained in Fields: Scheduling Parameters.

  4. Choose OK.

This section covers the following topics:

Fields: Scheduling Parameters

The fields of the tabbed page Scheduling Parameters are described in the following table.

Field Description
Estimated Elapsed Time The expected total running time (in minutes) for the job.
  • If not specified explicitly, this value is derived from the average running time of previous runs of the same job, displayed in the field directly below.

  • If this value is not equal to zero (0) for a permanent dummy job (job type Dummy Job) with a special type other than Execute as dummy (dummy due to a condition), this dummy job is executed for exactly the amount of time given here. This enables you to perform time simulations, etc.

  • Active scheduling parameters for a running dummy job:

    Modification of the estimated elapsed time causes the end time of the dummy job to be recalculated as sum of the start time and the new estimated elapsed time. If the new calculated end time is lower than the current time, the current time will be used instead.

  • Temporary dummy jobs with the job type Dummy Job and special type Execute as dummy (dummy due to a condition) execute for the amount of time defined as estimated elapsed time for the job.

  • For temporary dummy jobs with other special types (for example, dummy due to a condition), the defined estimated elapsed time is ignored. Temporary dummy jobs always have the execution time zero.

Special value: For jobs of the job type Subnetwork, 999999 can be specified. In this case, all start times after that are set to the ending times in the subnetwork.

Average  Average running time (in minutes) computed from the last 20 runs shown in the History Elapsed Time (min.) table.
History Elapsed Time (min.) Table containing the actual running times (in minutes) of the last 20 runs of the job.

The running time of the last 20 runs with non-zero elapsed times is used to compute the average time (in the Average field) the job needs to finish.

History elapsed times for multiple jobs (see also the Suffix Symbol field described in Job Maintenance):

  • For a job master, the table contains the elapsed times of all multiple active jobs, which were last activated by this job master.

  • For an active job, the table contains the elapsed times of all multiple active jobs whose names match the name of this active job.

Earliest Start Time The job will not be started before this time.

Use days later if the Earliest Start Time is more than one day later than the network start time.

You can specify the number of workdays or calendar days to be used for later starts: see Calendar days later | Workdays later below.

See also Processing of Time Frame Definitions.

For an active job, the Earliest Start fields contain the time calculated for the respective job run according to the definitions made in the corresponding job master. Both fields can be modified for the given job run only.

Latest Start Time  The job will not be started after this time.

If this time precedes the Earliest Start Time and days later is empty, days later is set to 1 so this time follows the Earliest Start Time.

You can specify the number of workdays or calendar days to be used for later starts: see Calendar days later | Workdays later below.

See also Processing of Time Frame Definitions.

For an active job, the Latest Start fields contain the time calculated for the respective job run according to the definitions made in the corresponding job master. Both fields can be modified for the given job run only.

Deadline Time Time by which the job must be finished.

If the job cannot be finished before this time, it is not submitted.

Dummy jobs with Estimated Elapsed Time not equal to zero (0) are finished at this time at the latest.

You can specify the number of workdays or calendar days to be used for later starts: see Calendar days later | Workdays later below.

See also Processing of Time Frame Definitions.

For an active job, the Deadline fields contain the time calculated for the respective job run according to the definitions made in the corresponding job master. Both fields can be modified for the given job run only.

Input fields for number of days and day type:

Calendar days later | Workdays later

(Applies to job masters only.)

You can use the input fields next to Earliest Start Time, Latest Start Time and Deadline Time to define a time frame that exceeds 24 hours. Enter the number of days (maximum is 999) you want to postpone a start time or deadline.

Use the drop-down list boxes to select the day type to be used for the specified start time or deadline: a calendar day or a workday as defined in the calendar linked to the schedule.

See also Processing of Time Frame Definitions.

Note:
The Entire Operation default settings provide the option to define later start times in units of hours instead of integer days, for time ranges that are not a multiple of 24.

Schedule Dependency A code shown in this read-only field indicates that this job has a schedule dependency.

The field is empty if no schedule dependency is defined for the job.

You can choose Modify to open a window where you can view, add or modify a schedule dependency.

See also Maintaining Schedule Dependencies for a Job.

Cyclic Interval This field is only available for cyclic jobs.

Wait time (in minutes) between two executions of a cyclic job (special type Cyclic execution).

Default: Monitor wait time.

Late Message See Sending a Late Message to One or More Users.
Account Info See Viewing Job/Network Accounting Information in the section Job Maintenance.

Maintaining Schedule Dependencies for a Job

You can define particular days of the week, month or year when a job (or all jobs of a network, see Adding and Modifying a Time Frame Definition) executes as a temporary dummy due to schedule condition (see also Temporary Dummy Jobs).

You can also define day dependencies for a job input condition. If defined, the job executes without performing an input condition check.

If a day dependency is not defined (default) at the job or network level, or for a job input condition, the job executes normally, that is, exactly as defined in the job master.

The date and time defined for job execution on the Scheduling Parameters page is then checked against the current schedule of the current network, or the current calendar. For jobs in a subnetwork, we recommend you to specify that the topmost calling network is checked instead of the current network by using Check schedule of the topmost calling network option.

Prerequisite for Concatenated Jobs

If you want to deactivate single or multiple jobs in a chain of dependent jobs, for all jobs in the chain, the option End-of-Job Action must be set to No impact on the job result. Otherwise, errors can occur during End-of-Job processing.

See also Excluding a Job from Actual Execution.

Note:
The job execution date and time can be different (one or more days later) from the job activation date and time.

Start of instruction set To define schedule dependencies at the job level

  • On the tabbed page Scheduling Parameters of the Maintenance Job Master window, choose Modify next to Schedule dependency.

    A Schedule Dependency Definition window similar to the example below opens:

    graphics/scheduledependency_inputcondition.png

    The input fields and options in the window are described in Fields: Schedule Dependency Definition.

This section covers the following topics:

Defining Schedule Dependencies for an Input Condition

You can define an input condition that is not used on all activation dates of a job network. This can be done for the following reasons:

  • A predecessor job or network does not run on all schedule dates of the successor job or network.

  • Some predecessor jobs are also schedule-dependent.

Start of instruction setTo define schedule dependencies for an input condition

  1. From the table on the tabbed page Input Conditions, select an input condition and choose Schedule Dep..

    A Schedule Dependency Definition window opens.

    The fields contained in the window correspond to the fields of the Schedule Dependency Definition for Job window. They are explained in Maintaining Schedule Dependencies for a Job.

  2. Make your definitions.

  3. Choose OK.

    The schedule dependency is allocated to the input condition and the window closes.

    The schedule dependency is now indicated in the Sched.Dep. column.

Fields: Schedule Dependency Definition

The input fields of the Schedule Dependency Definition window provided for a job, a job input condition and a network are described in the following table:

Field Description
Check schedule of the topmost calling network Possible check box settings:
unchecked Checks the schedule of the current network (default).

This setting is recommended for jobs in main networks.

checked Checks the schedule of the topmost network that calls the job.

This setting is recommended for jobs in subnetworks.

Usage           Possible selection options:
Only  For a job or condition:

The job or condition is activated only if the execution date satisfies the criteria entered in the Type, Period and Position fields.

For a network:

The object is valid only for schedule days matching the following definitions.

After holiday too Like Only, but the first workday after an otherwise matching holiday is valid, too.
Before holiday too  Like Only, but the last workday before an otherwise matching holiday is valid, too.
Except  For a job or condition:

The job or condition is activated except when the execution date satisfies the criteria entered in the Type, Period and Position fields.

For a network:

The object is valid for all schedule days except if they match the following definitions.

Type            Possible selection options:
Is holiday  Any holiday (no period and/or position required).

The relative position to the holiday can be specified.

Is workday Any workday (no period and/or position required).

The relative position to the workday can be specified.

Calendar day  Calendar day within the defined period.

A relative position refers to the real calendar period.

Workday  Workday within the defined period.

A relative position refers to the workdays in the period.

Schedule day  Schedule day within the defined period.

A relative position refers to the schedule days in the period.

Period       Possible selection options:
Week  Current week.
Month  Current month. 
Year  Current year, with relative or exact position.
Position Schedule dependency position.

The position within the defined period depending on the specified type.

Relative position:

  • Positive values (+) are relative to the period begin, negative values (-) are relative to the period end. For the types Is holiday and Is workday, this is the day difference.

    Valid value ranges are:

    For a week: -7 to -1 and +1 to +7
    For a month: -31 to -1 and +1 to +31
    For a year: -366 to -1 and +1 to +366

    Note:
    You can specify up to three days for the period week. Example: 24 is Tuesday and Thursday.

Exact position:

  • Fixed month (1 - 12) and day (1 - 31) of the year.

Only applies if Calendar Day is selected for Type and Year for Period.

See also Examples of Schedule Dependency Definitions.

Examples of Schedule Dependency Definitions

The following are example combinations for day calculation:

Type Period Position or Month/Day Calculated Day
Calendar day Week +2 Tuesday
-1 Sunday
Month +1 01
-1 28 ... 31
Year +1 January 01
-3 December 29
  Month: 4, Day: 9 April 09

(yearly, including leap years)

Workday Month -1 Last workday of the month
234 Second, third and fourth workday of the month
Is holiday n/a +1 Day after a holiday

Deleting Schedule Dependency Entries

Start of instruction setTo delete a schedule dependency entry for a job

  1. On the tabbed page Scheduling Parameters, choose Modify next to the entry in the Schedule dependency field.

    A Schedule Dependency Definition window opens.

  2. Clear the Usage field by selecting a blank option from the drop-down list box.

    All entries are removed from the window.

  3. Choose OK.

    The Schedule Dependency Definition window closes and the Schedule dependency entry is removed from the Scheduling Parameters page.

Sending a Late Message to One or More Users

You can define one or more users (recipients) to receive job-related standard messages that are sent when a job could not be executed in the defined time range.

Start of instruction set To inform users that a job could not be executed

  1. On the tabbed page Scheduling Parameters, choose Late Message.

    A Maintenance Message and Message Recipients window opens.

  2. Change, add or remove a message recipient as described under Recipients in Step 3 of To view or change a notification message in the section Defining Notification Messages (Job Maintenance).

Note:
You cannot change the text of job-related standard messages.