You can specify to release an explicitly kept resource as End-of-Job action.
It is possible to release a resource held by any other job of this network with the ‘Keep’ option. The released amount is equal to the kept amount.
Field | Meaning |
---|---|
Resource | The resource to be released. The resource can be selected by usage of a wild card. |
Execute if temporary Dummy | If Y or N is specified here, the End-of-Job action will be
executed according to this definition, if the job was executed as a temporary
dummy job. If the field is left empty, the defaults for the action apply. |