Integration Server 10.3 | Integration Server Administrator's Guide | Managing Packages | Finding Information about Your Packages | Viewing the Packages that Reside on Your Server | Determining Whether the Server Successfully Loaded the Package
 
Determining Whether the Server Successfully Loaded the Package
The server displays a status in the Loaded? column of the Packages screen.
Status
Indicates that
green check mark icon
Yes
The server successfully loaded all elements associated with the package. The elements in the package are available. The server also displays this status if the package is empty.
yellow check mark icon
Partial
The server did not load one or more of the elements associated with the package. The elements that the server successfully loaded are available. For instructions on how to determine which elements the server did not successfully load and why, see Displaying Information about a Package.
No
The server did not load any of the elements associated with the package. None of the elements are available. For instructions on how to determine why the server could not load the elements, see Displaying Information about a Package.
When the server is started, it automatically loads into memory all elements that are in enabled packages. If a package is disabled at startup, the server loads the elements into memory when the package is enabled. You can manually reload a package if necessary. For instructions on reloading a package, see Reloading a Package.