Suspending a Single User Task
When you suspend a user task, it remains scheduled, but does not execute until you resume its execution. If a task expires while suspended, the server marks it Expired.
Note: If your
Integration Server is part of a cluster and you are suspending a task that has been scheduled to run on all
Integration Servers in the cluster, you can suspend the child tasks individually or you can suspend all the tasks at once by suspending the parent task. For more information about scheduled tasks that run on all servers in a cluster, see
Target Node Options.
To suspend a scheduled user task
1. Open the Integration Server Administrator if it is not already open.
2. In the Server menu of the Navigation panel, click Scheduler.
3. Locate the task in the Services list, and click the icon in the Status column to suspend the task. The server displays a screen to confirm you want to suspend the task. Click OK. The server replaces the icon with Suspended to indicate that the task is now suspended.