This column | Reports |
Stage | The name of the stage. |
Started | The number of instances that began during the time range. |
Running | The number of instances that were still in progress at the end of the time range. |
Incomplete | The number of instances that were running but did not complete and that were associated with a process instance that did complete during the time range. |
Completed | The number of instances that completed (successfully or not) during the time range. |
Alarms | The number of instances that breached a condition of the stage. |
Cycle Time | The average cycle time for instances that completed during the time range. |
Details | Metadata about the stage. |
Column | Description |
SID | The stage instance ID. It serves as a link to the Optimize Process Instances Detail page, which provides additional information about this process instances related to this stage. |
Stage Name | The name of the stage. |
Stage Date and Time | Time when the instance began. |
End Date and Time | Time when the instance ended. |
PID | The ID of the process instance. It serves a link to the Optimize Stage Instances Detail page, which provides additional information about the stage instance. |
Status | The status of the stage instance. Statuses are as follows: - Indicates that the stage instance was started during the specified time range. - Indicates that the stage instance was still in progress during the specified time range. - Indicates that the stage instance did not complete, though the associated process instance did complete during the specified time range. - Indicates that the stage instance completed during the specified time range. |
Cycle Time | The duration of the instance (for completed instances only). |
Actions | Actions you can take for this instance. Click the email icon and complete the provided email form to send details about the stage instance to other interested parties. Click the Escalation icon and complete the provided form to create an escalation action event. |