Schedule the execution of further tasks or procedure files.
Processing starts after processing of the current procedure file has finished.
Using SCHEDTOP, tasks or procedure files
are scheduled on a first-in-first-out (FIFO) basis. Using
SCHEDULE, tasks or procedure files are scheduled on
a last-in-first-out (LIFO) basis.
Caution:
Do not use the commands SCHEDULE and
SCHEDTOP within the same procedure file or group of
nested procedure files.
SCHEDTOP {task|procedure} [parameter] ...
SCHEDULE {task|procedure} [parameter] ...
task is a task defined to Entire Connection.
procedure is a procedure file defined to Entire Connection.
parameter is any valid input parameter for the task or procedure file.
Schedule the task BUDGET, which runs a Natural
program on the mainframe and downloads data to the ASCII file
Budget.ncd:
SCHEDULE BUDGET Budget.ncd
Schedule the task BUDGET as the first task to be
executed after processing of the current procedure file has finished:
SCHEDTOP BUDGET Budget.ncd
Schedule a task or procedure file whose name is defined by the
variable #PARM1:
SCHEDULE #PARM1