Global Scheduled Synchronization Task - On Failure Task

The Global Scheduled Synchronization Task entered into the On Failure Task text box runs after every failed synchronization. For example, you could choose to send an e-mail to Operations to show that a task failed, so that you can receive instructions on how to correct the problem.

Image106.jpg


For example:

  1. Compose a command line that resembles the following:

c:\utils\epsendmail nickd@connx.com, operations@connx.com, "Task Succeeded", "Global Synchronization Task succeeded", 255.255.255.255

  1. Test the command through the Global On Demand Synchronization On Failure Task text box, and then cut-and-paste it into the On Failure Task text box under Global Scheduled Synchronization tasks. Instead of 255.255.255.255, enter the TCP/IP address of your SMTP mail server.